Snel.com - SmartDC dark site tests Q3 – Maintenance details

SmartDC dark site tests Q3

Completed
Scheduled for September 05, 2023 at 06:00:00 – 08:00:00

Affects

SmartDC, Rotterdam NL

Under maintenance from 6:00 AM to 8:00 AM

SmartDC power network

Under maintenance from 6:00 AM to 8:00 AM

Snel.com network infrastructure

Under maintenance from 6:00 AM to 8:00 AM

Pure Performance VPS platform

Under maintenance from 6:00 AM to 8:00 AM

Cloud VPS platform

Under maintenance from 6:00 AM to 8:00 AM

My.snel.com - client area

Under maintenance from 6:00 AM to 8:00 AM

Updates
  • Completed
    September 05, 2023 at 08:00:00
    Completed
    September 05, 2023 at 08:00:00

    Maintenance has completed successfully

  • In progress
    September 05, 2023 at 06:00:01
    In progress
    September 05, 2023 at 06:00:01

    Maintenance is now in progress

  • Planned
    September 05, 2023 at 06:00:00
    Planned
    September 05, 2023 at 06:00:00

    On the 5th of September 2023 SmartDC, the datacenter in which our servers are located, will perform a dark site test.

    Maintenance start (CET/CEST): 5th September 2023 08:00
    Maintenance end (CET/CEST): 5th September 2023 10:00
    Maintenance duration: 2 hours

    Expected impact: If all goes as planned no services will be affected during this maintenance. In the unfortunate event that something unexpected happens our technical support team is standby.