Snel.com - SmartDC on-load tests Q2 – Maintenance details

SmartDC on-load tests Q2

Completed
Scheduled for May 03, 2022 at 03:00:00 – 06:00:00

Affects

SmartDC, Rotterdam NL

Under maintenance from 3:00 AM to 6:00 AM

SmartDC power network

Under maintenance from 3:00 AM to 6:00 AM

Updates
  • Completed
    May 03, 2022 at 06:00:00
    Completed
    May 03, 2022 at 06:00:00

    Maintenance has completed successfully

  • Update
    May 03, 2022 at 03:00:01
    In progress
    May 03, 2022 at 03:00:01

    Maintenance is now in progress

  • In progress
    May 03, 2022 at 03:00:01
    In progress
    May 03, 2022 at 03:00:01

    Maintenance is now in progress

  • Planned
    May 03, 2022 at 03:00:00
    Planned
    May 03, 2022 at 03:00:00

    On the 3rd of May 2022 SmartDC, the datacenter in which our servers are located, will perform a generator onload test.

    Maintenance start (CET/CEST): 3rd May 2022 05:00 hours **Maintenance end ** (CET/CEST): 3rd May 2022 07:00 hours Maintenance duration 2 hours

    Expected impact: If all goes as planned no services will be affected during this maintenance. In the unfortunate event that something unexpected happens our technical support team is standby.