Snel.com - black building test' SmartDC 7th of May 2019 – Maintenance details

black building test' SmartDC 7th of May 2019

Completed
Scheduled for May 07, 2019 at 05:30:00 – 05:30:00

Affects

SmartDC, Rotterdam NL

Under maintenance from 5:30 AM to 5:30 AM

SmartDC power network

Under maintenance from 5:30 AM to 5:30 AM

Updates
  • Completed
    May 07, 2019 at 05:30:00
    Completed
    May 07, 2019 at 05:30:00

    On the 7th of May SmartDC, the datacenter in which our servers are located, will perform a planned Back up power test. This will be a so-called 'black building test'.

    Explanation: A Black Building test is a test in which the full IT load will be passed on to the backup power installation. During this test, all UPS'es, generator and power switches on the main board will be tested for its correct operation. Nonpreferent electrical power, e.g. B-feed can drop during this test. It will take approximately 15 seconds to switch from grid power to backup power. Afterwards the generators will be live for another hour to test their performance.

    This test will be conducted by trained and certified technical staff accompanied with our vendors.


    Maintenance start: 07/05/2019 07:30 CEST Maintenance end: 07/05/2019 16:00 CEST Expected impact: If all goes as planned no services will be affected during this test. In the unfortunate event that something unexpected happens our technical support team is standby.